UNIT OUTAGE DETAIL FOR DATE 28/3/2017 AT 6:00HR

SR. NO. UNIT CAP (MW) OUTAGE DTD OUTAGE TIME FORCE PLAN (MW) AVAI- LABLE SCHEDULE DT. REVISED EXPECTED DATE Reason
1 UTPS-2  120  08 DEC 16  15:00    120        Canal work  
2 UTPS-1  120  08 DEC 16  15:00    120        Canal work  
3 STPS-2  120  22 MAR 17  00:00  120          Long restoration time 
4 STPS-1  120  22 MAR 17  00.00  120          Long restoration time 
5 UTPS-4  200  07 Dec 16  00:00    200    26 APR 17    AOH 
6 UTPS-5  210  06 DEC 16  23:57    210    06 MAR 17  28 MAR 17  AOH 
7 DGB-GT3+STG  375  15 DEC 16  16.53      375      Costly generation 
8 WTPS-6  210  16 MAR 17  00    210    07 APR 17    AOH 
9 GTPS-4  210  05 MAR 17  00:00    210    03 APR 17    AOH 
10 DGBP 2  112  20 MAR 17  04:48  112      22 MAR 17  13 APR 17  High exhaust temperture 
11 UGPP-2  375  25 MAR 17  19:57      375      Costly generation 
    Total 352 1070 750     2172
PRIVATE SECTOR
1 AE Co-C  60(0)  01-JUN-15  19:50          RSD Load regulation 
2 UNOSUGEN  382(0)  29-FEB-16  19:39          RSD Load Regulation 
3 DGEN 52  400(0)  31-MAR-16  23:58          RSD Load regulation 
4 DGEN 53  400(0)  31-MAR-16  21:45          RSD Load regulation 
5 GSEG-GT2+STG  52+26  16 DEC 16  16:38      78      RSD Costly generation  
6 GSEG GT1+STG  52+26  16-DEC-16  16:41      78      RSD Costly generation 
7 GPPC GT1+STG  351  01 FEB 17  00:00      351      Available on costly gas 
8 SUGEN-2  383(0)  16 FEB 17  16:56          RSD 
9 GPPC GT-2+STG  351  01 FEB 17  00:00      351      Available on costly gas 
10 CLPI GT 1+STG  218  21 MAR 17  00:00    218        PSD 
11 SUGEN 30  383(0)  29 DEC 16  13:08          RSD 
12 OPGS-2  150 (0)  01 FEB 17  0:00          Less schedule 
13 BECL 1  250  10 FEB 17  22:25  250      04 APR 17    Combustion chamber leakage problem 
14 EPGL-1  600  01 MAR 17  06.56  500      15 MAR 17  30 MAR 17  hydrogen leakage 
15 CLPI-GT2+STG  218  21 MAR 17  00:00    218        PSD 
16 APL-6  660(500)  03 MAR 17  20:46  500      20 MAR 17  02 APR 17  Hydrgen leakage 
17 APL-1  330(250)  05 MAR 17  18:58  250          Coal shortage 
18 CLPI-GT3+STG  218  21 MAR 17  00:00    218        PSD 
19 APL-2  330(250)  07 MAR 17  02:01  250          Coal shortage 
20 ACBIL-1  135(100)  14 MAR 17  00:00    100    10 APR 17    AOH 
21 EPGL-2  600  16 MAR 17  14:46  500      30 MAR 17    BTL 
22 APL-3  330(250)  17 MAR 17  22:16  250          TERBINE VIBRATION HIGH 
23 SLPP-1  125  19 MAR 17  06.31  125      22 MAR 17  28 MAR 17  BTL 
24 OPGS-1  150(0)  26 MAR 17  00:00          Less schedule 
25 GSEG stage 2  351  26 MAR 17  16:27      351      RSD Costly generation 
26 ACBIL-2  130(100)  27 MAR 17  13:30  100          BTL 
    Total 2725 754 1209     4688
CENTRAL SECTOR
1 KAPP-2  220 (63)  01-JUL-15  14:09  63      31-AUG-15  01 APR 17  Reactor channel problem 
2 KAPP-1  220  11 MAR 16  09:00  63      01-MAY-16  01 APR 17  Leakage in primary heat transfer system 
3 Kawas-2A+STG  106(47)  22 JAN 17  10:37      47      Costly generation 
4 Kawas-2B+STG  106(47)  22 JAN 17  16:30      47      Costly generation 
5 VSTPS-5  210(38)  27 MAR 17  00:26    38    28 APR 17    Boiler ESP R&M work 
    Total 126 38 94     258
    GRAND TOTAL 3203 1862 2053     7118
 